Using CMMI to Improve Earned Value Management

• SEI Report
This technical note provides guidance for integrating Earned Value Management (EVM) with CMMI for cost-effective process improvement and appraisal.
Publisher

Software Engineering Institute

CMU/SEI Report Number
CMU/SEI-2002-TN-016
DOI (Digital Object Identifier)
10.1184/R1/6585704.v1

Abstract

For organizations using Earned Value Management (EVM) or that plan to implement EVM during Capability Maturity Model Integration (CMMI) implementation, this technical note provides guidance for cost-effective process improvement and appraisal. Mapping and comparison tables between CMMI and the U.S. national standard on EVM are provided. These tables can be used to identify practices within CMMI that are not included in the EVM standard but, if added to an organization's processes, will strengthen adherence to EVM principles. The tables also can be used to develop instruments that will provide evidence to an appraisal team to enable it to quickly verify and validate specific practices based upon effective implementation of EVM.  

Furthermore, information such as glossary components, typical work products, and examples are included in this technical note to aid those using CMMI for process improvement. For organizations using technical performance measurement, a primary base measure for earned value, additional guidance and information is provided. Finally, additional references and an EVM glossary are provided.

Cite This SEI Report

Solomon, P. (2002, October 1). Using CMMI to Improve Earned Value Management. (SEI Report CMU/SEI-2002-TN-016). Retrieved November 20, 2026, from https://doi.org/10.1184/R1/6585704.v1.

@techreport{solomon_2002,
author={Solomon, Paul},
title={Using CMMI to Improve Earned Value Management},
month={Oct},
year={2002},
number={{CMU/SEI-2002-TN-016},
institution={Software Engineering Institute, Carnegie Mellon University},
doi={10.1184/R1/6585704.v1},
url={https://doi.org/10.1184/R1/6585704.v1},
note={Accessed: 2026-Nov-20}
}

Solomon, Paul. "Using CMMI to Improve Earned Value Management." (CMU/SEI-2002-TN-016). Software Engineering Institute, Carnegie Mellon University. Software Engineering Institute, October 1, 2002. https://doi.org/10.1184/R1/6585704.v1.

P. Solomon, "Using CMMI to Improve Earned Value Management," Software Engineering Institute, Carnegie Mellon University. Software Engineering Institute, SEI Report CMU/SEI-2002-TN-016, 1-Oct-2002 [Online]. Available: https://doi.org/10.1184/R1/6585704.v1. [Accessed: 20-Nov-2026].

Solomon, Paul. "Using CMMI to Improve Earned Value Management." (SEI Report CMU/SEI-2002-TN-016). Software Engineering Institute, Carnegie Mellon University, Software Engineering Institute, 1 Oct. 2002. https://doi.org/10.1184/R1/6585704.v1. Accessed 20 Nov. 2026.

Solomon, Paul. Using CMMI to Improve Earned Value Management. CMU/SEI-2002-TN-016. Software Engineering Institute. 2002. DOI: 10.1184/R1/6585704.v1. https://doi.org/10.1184/R1/6585704.v1

Please note that current and future CMMI research, training, and information has been transitioned to the CMMI Institute, a wholly owned subsidiary of ISACA.